courses:456:2022:projects:456-2022-06:project-06 [2022/05/14 04:48] โ€“ [Reports and presentations] jhan62courses:456:2022:projects:456-2022-06:project-06 [2022/05/17 18:13] (current) โ€“ [Milestones and Status] jhan62
Line 53: Line 53:
   - Milestone name: System Integration   - Milestone name: System Integration
     * Planned Date: Week 8     * Planned Date: Week 8
-    * Status: In Progress+    * Status: Finished
   - Milestone name: Improvements/Optimization   - Milestone name: Improvements/Optimization
     * Planned Date: Week 12     * Planned Date: Week 12
Line 59: Line 59:
   - Milestone name: Final Organization and Produce results report   - Milestone name: Final Organization and Produce results report
     * Planned Date: Week 12     * Planned Date: Week 12
-    * Status: Not Yet Begun+    * Status: Finished
   - Milestone name: Final Presentation   - Milestone name: Final Presentation
     * Planned Date: Week 12     * Planned Date: Week 12
-    * Status: Not Yet Begun+    * Status: In Progress
 ======Reports and presentations====== ======Reports and presentations======
  
courses/456/2022/projects/456-2022-06/project-06.1652503733.txt.gz ยท Last modified: by jhan62




ERC CISST    LCSR    WSE    JHU